FULLY IN-GROUND FIBERGLASS ENDLESS POOL CONSTRUCTION SEQUENCE
1
2
3
4
Excavate and prepare pit for arrival of shell. A level, compacted sand bed at least 3" deep is required. If ground water is present
or may be an issue install a gravel sump with a 10" diameter vertical pipe at the front of the pool. Ground water must never be
allowed to exceed the water level in your pool. Run conduit for power and two hydraulic lines between the hydraulic power
unit and the equipment space at the front of the pool (Four 1-1/2" schedule 40 flexible PVC pipes).
Receive pool and lower into position. Level pool. Backfill with sand while filling with water. Using 3/4" plywood, frame out
equipment space at the front of pool. Install sump if necessary. Plumb equipment.
Continue filling while backfilling with sand. Run power and hydraulic hoses through conduit to
front equipment space.
Pour concrete surround and build removable trap door. Install swim current generator.